Signal cable in place

The 1770 m signal cable going from the Builai intake to the power house is now installed. The cable needed to be stretched through pipes buried in the ground, as the cable passes through cultivated land, and also in order to protect the environment. This challenge involved several teams coordinating their pulling, and was completed over two (long) days.

Photo: Basil Rolandsen (www.bouvet.info)